Design and construction of extensions to water and sewer mains are undertaken by consultants accredited by us. The property owner is required to employ a consultant to: design and cost the project, supply materials, and arrange construction of works using accredited pipelayers to our standards and specifications.
The consultant will charge a management fee for these services, so you may wish to obtain several quotes. The process is as follows:
- Contact an accredited consultant who will advise you on the costs and extent of the work involved.
- The consultant prepares the design and estimates for construction of the works submits these documents to us.
- We then send you an agreement, which includes details of our charges and connection fees.
- Sign and return two copies of the agreement and pay any charges.
- Construction can proceed under the management of the design consultant. All works must be undertaken by one of our accredited pipelaying contractors.