$13 million sewer project on (and under) track

Home / Media/Notices / Media releases / 2015 / 01 / $13 million sewer project on (and under) track /

$13 million sewer project on (and under) track

Gippsland Water has completed another critical phase of its $13 million Warragul Sewer Upgrade.

The local provider of water and sewerage services recently completed the delicate job of burrowing more than 100 metres underneath Princes Way and railway line to make way for the new pipeline.

The works, which follow more than two years of planning and design in consultation with VLine and VicTrack, were completed over two nights without any impact to train services.

“We have now successfully completed two of the three critical sections of this final phase of the $13 million Warragul central trunk sewer replacement project. We thank VLine and VicTrack for their involvement in the project,” Mr Paul Clark, General Manager of Customer Service and Communications at Gippsland Water, said.

“This investment allows for future development of the Warragul township along with fast-growing areas to the west and south of Warragul. Previously unsewered properties close to the Warragul CBD will also be serviced,” he added.

“We’re delighted to be close to finishing this major project for the Baw Baw and Warragul community. It will allow for future growth and prosperity in the region as well as provide a more reliable and efficient sewerage solution for our local customers,” concluded Mr Clark.

The new sewer main also has the capacity for emergency storage within the pipeline system, which means Gippsland Water is able to decommission two existing pump stations currently located on the western edge of Warragul.

Howitt Street is the next major set of works to be conducted as part of the project. This section of work is expected to be completed by the end of March. The entire four kilometre stretch of new underground sewer main is on track for completion in June 2015.

Traffic and parking disruptions will occur during this time. Gippsland Water thanks the community for its patience during this project.


Share this page on your own social media pages:  

All media enquiries:

Please contact the Communications and Engagement Manager on (03) 5177 4793 or 0448 905 833



Other news articles

About Us

Gippsland Water supplies fresh clean drinking water to more than 70,000 customers, and wastewater services to more than 63,000 customers across an area of more than 5,000 square kilometres. It maintains a $1 billion infrastructure network, which includes more than 2,000 kilometres of water mains, 15 water treatment plants, over 1,700 kilometres of sewer mains and 14 wastewater treatment plants.

Read More

Choose Tap

Choose Tap aims to promote the benefits of drinking tap water as part of a healthy lifestyle and as an alternative to bottled water.

Read More

Contact Us

Gippsland Water Head Office, 55 Hazelwood Road, Traralgon, VIC, 3844

Phone: 1800 050 500
Fax: (03) 5174 0103
Interpreter service: 131 450
TTY: 1800 555 677
Email: contactus@gippswater.com.au

Get Directions