Infrastructure sequence plans

Information to assist with council awareness and developers

About our infrastructure sequence plans

We've developed infrastructure sequencing plans to be used for: 

  • our shared asset budget 
  • council awareness to understand our preferred direction for future growth 
  • to give developers a visual understanding of our infrastructure sequencing. 

These plans apply to the towns and are intended as a guide, including future shared assets. 

The 26/27 infrastructure sequence plans include the following towns and changes: 

General Updates 

Areas with a Sequence timing of 0 where significant development has occurred have been removed from ISPs 

If these areas still have considerable development to occur, they have been changed to a Sequence timing of 1.  

This aligns all Sequence 1 timings of all towns to the current year.  

Areas where no shared assets are required to develop have been changed to a sequence timing of 1. 

Drouin 

  • Water shared asset constructed and removed from plan along Illawarra Blvd 
  • 0b, 1e removed from plans  
  • 0o, 0p & 3b changed to a Sequence 1 (1c, 1b & 1o, respectively)  
  • 1m & 3d changed to a Sequence 2 (2d & 2e, respectively)  
  • Sequence 3 was pushed out three years 

Churchill 

  • Sections of water and sewer shared assets in 2b have been constructed and removed from plans 
  • 0d removed from plans 
  • 0a combined with 1b 
  • Sequence 2 was pushed out one year 

Heyfield 

  • Sewer shared asset in 2b removed from plan due to reduced capacity requirements 
  • 2b & 2c changed to a Sequence 1 (1i & 1j respectively)  

Maffra 

  • 0b changed to a Sequence 1 (1g) 
  • Sequence 2 was pushed out one year 

Moe- Newborough 

  • Rising main shared asset from 4a/4b SPS realigned along edge of Lake Narracan and along Hayes Road to sewer shared asset 
  • 1t removed from plans 
  • Sequence 2 brought in seven years; Sequence 3 pushed back one year 

Morwell 

  • Water shared assets along Panoramic Drive & along the eastern boundary of 1d along Latrobe Road were constructed and removed from plan 
  • Sewer shared asset from Crinigan Road SPS realigned along Crinigan Road and along Pimelea Street to Proposed SPS in 3b 
  • 1g extended North to include lots to align with development staging 
  • 2k changed to a Sequence 1 (1i)  
  • 1b & 1c changed to a Sequence 2 (2q & 2r, respectively) – shared asset required 
  • Sequence 2 was brought in three years & Sequence 3 was brought in five years 

Sale 

  • 2b removed from plans 
  • 1k (end of Glen Campbell Crt) added to plans  
  • 2c changed to a Sequence 1 (1j) 
  • 2e & 2f changed to a Sequence 3 (3c & 3d, respectively) 
  • 3b changed to a Sequence 4 (4a) 
  • Sequence 2 was pushed out four years; Sequence 3 was brought in four years & Sequence 4 was set at 65/66 

Stratford 

  • North area of 1b (North of Carter Street) changed to a Sequence 2 (2a) – shared asset required 
  • Sequence 2 timing set at 41/42 

Trafalgar 

  • 1e removed from plans 
  • Sequence 2 was pushed out one year & Sequence 3 was pushed out two years 

Traralgon 

  • Water shared asset constructed and removed from plan along Broadway Boulevard & Hollywood Boulevard in 2e 
  • 1j (Ashworth Drive) added to plans 
  • 1b, 1d & 1f removed from plans 
  • 2b divided into two sewer catchments (2b & 1n) 
  • 2a, 2d & 2f changed to a Sequence 1 (1m, 1k & 1l, respectively) 
  • Sequence 2 was pushed out seven years & Sequence 3 was pushed out four years 

Warragul 

  • Water shared asset from McCubbin Drive in 2a realigned with development and constructed sections removed 
  • Shared asset rising main along Copeland Road reduced in length 
  • 1i, 1k, 1m, 1n & 2b removed from plans  
  • 2d, 2e, 2h & 3e changed to a Sequence 1 (1o, 1p, 1q & 1s, respectively) 
  • Sequence 2 was pushed out three years; Sequence 3 was pushed out one year & Sequence 4 was brought in two years 

Wurruk 

  • 0a changed to a Sequence 1 (1b)  

Yarragon 

  • 0c removed from plans  
  • 0a changed to a Sequence 1 (1e) 
  • 1f added to plans 
  • 1c & 1d were combined (1c) 
  • Sequence 2 was pushed out nine years 

 

The establishment of reimbursement rate is set by the signing of the Developer Works Deed. The reimbursement rate is only set and locked at the time of signing. The Deed allows a year for the completion of the works. 

If the works are not completed within a year, we may execute a new Developer Works Deed and apply the reimbursement rate at that time. 

When developing please contact us for further guidance.